Participants: Burbank (5%), Los Angeles (92%), Pasadena (3%)
About Milford I
The Milford I Prepaid Wind Project is a 204 MW wind farm in Milford, Utah. The Facility commenced commercial operation on November 16, 2009.
Fiscal Year 2019-2020
This fiscal year Milford I delivered 418,275 MWhs, realizing a 23% net capacity factor.
Participants: Glendale (5%), Los Angeles (95%)
About Milford II
The Milford II Prepaid Wind Project is a 102 MW expansion of the Milford I Wind Farm in Milford, Utah. The Milford II Prepaid Wind Project achieved commercial operation on May 2, 2011.
© 2024 SCPPA . All rights reserved. | SCPPA