Springbok I, II, and III



Participants: Los Angeles (100%)

About Springbok I
The Springbok I Project is a 105 MW solar project located approximately 4 miles north of California City and one mile southwest of the unincorporated town of Cantil, California. The project achieved commercial operations on July 11, 2016.

Fiscal Year 2021-2022
This fiscal year Springbok I delivered 302,453 MWhs, realizing a 33% annual net capacity factor.




Participants: Los Angeles (100%)

About Springbok II
The Springbok II Project is a 155 MW solar project located approximately 4.5 miles north-northwest of California City and to the south-southwest of the unincorporated town of Cantil, California. Springbok II is adjacent to Springbok I. The project achieved commercial operations on September 6, 2016.

Fiscal Year 2021-2022
This fiscal year Springbok II delivered 421,055 MWhs, realizing a 31% annual net capacity factor.



Participants: Los Angeles (100%)

About Springbok III
The Springbok III Project is a 90 MW solar project located approximately 4.5 miles north-northwest of California City and to the south-southwest of the unincorporated town of Cantil, California. Springbok III is adjacent to both Springbok I & II. The project achieved commercial operation on July 19, 2019 and includes a 1.5 MW test battery to assist with various operational issues.

Fiscal Year 2021-2022
This fiscal year Springbok III delivered 220,158 MWhs, realizing a 28% annual net capacity factor.